Takt time is the pace production must hold to match customer demand: available production time divided by units of customer demand for the same period.

What it is

See it move

Loading infographic...

A workshop operates 450 minutes a day and customers demand 90 units a day. Takt time is 450 ÷ 90 = 5 minutes per unit — the pace the line must hold to keep up with orders. If the line's measured cycle time is 6 minutes per unit, it is running slower than demand requires; at 4 minutes, it has slack capacity.

The formula

LaTeX
TT=TavailDTT = \frac{T_{avail}}{D}

Variables

Available production time (minutes)
Customer demand (units) for the same period (units)

Gives the pace, in time per unit, that production must hold to exactly match customer demand for the period.

Check yourself

PracticeCORE

A packing line runs for 384 minutes a day and must meet daily customer demand of 96 units. What is the takt time?