Theoretical capacity

Theoretical capacity is the maximum output a plant could produce running flat out with zero downtime, holidays or maintenance — an unreachable ceiling used only as a reference point.

ByHoang TruongUpdated

See it move

Loading infographic...

A factory sets its overhead rate using theoretical capacity of 60,000 units against €600,000 of budgeted fixed overhead, giving €10 per unit. Actual output of only 40,000 units absorbs 40,000 times €10, or €400,000, leaving €600,000 minus €400,000, or €200,000, of overhead unrecovered — simply because no plant produces at the theoretical rate.

Where it fits
SubjectCost AccountingAdvancedTopicAbsorption & Variable CostingAdvancedTopicOverhead Allocation & ABCAdvanced

The formula

LaTeX
r=FOHKr = \frac{FOH}{K}

Variables

Overhead absorption rate (€ per unit)
Budgeted fixed overhead ()
Capacity level used as the denominator (units)

The rate at which fixed overhead is spread over output; choosing theoretical capacity as K makes the rate look low but leaves most overhead under-absorbed in practice.